Steel structure warehouse hoisting process and hoisting plan-Chapter 1

Time:[2021-9-25]  Hits:2378

Hoisting process

 

Positioning --- Calibration Height --- Column Top Bolt Embedded --- Calibration Height - Elastic Line - Column Installation - Steel Beam Installation - Secondary Structure Installation --- --Welding----Repainting----Completion

 

 

Steel column installation process


A,Lifting of steel columns

 

1.Re-test the foundation, including the exposed length of the anchor bolt, the displacement deviation of the anchor bolt center line to the reference line, the distance between the anchor bolts, and the foundation elevation. The unqualified ones can be handled before lifting.

 

2.In order to control the installation elevation of the column, a 500mm position is also marked on the visible cross section of the column in advance for fine-tuning and correction of the elevation during installation. Install the steel column on the basis of qualified retest, first tie the column with a single steel wire rope, and choose the position of the lifting point at a position 1/3 of the length of the column from the end of the column. The column is lifted by the rotation method, and the steel column is lifted and sent to the installation position. The lashing place should be padded.

 

 

B, the correction of the steel column

 

1.Draw the center line in advance on the visible surface of the column, and then use the theodolite to adjust the verticality of the column in two mutually perpendicular directions.

 

2.Control the verticality of the column by measuring the distance between the inner side of the column and the control line on the building.

 

3.The adjustment of the elevation, axis and verticality deviation of the column are related to each other, and the correction work will be completed when all the standards are met.

 

 

Steel beam installation process

 

Unload the steel beams to the vicinity of each column, hoist them to the floor with a car, and then install them by mast cranes. The main beams with some heavy components can be platform craned with car cranes. The secondary beam can be installed with a self-made wheeled crane (5t). Starting from the third zone, the main girder, the secondary girder and then the purlin, the steel girder shall be hoisted by masts one by one according to the number. Only when the two ends of the girder are fastened with bolts (or spot welded firmly), the hooks can be loosened and the others are hoisted in sequence Steel beams. Weld after passing the inspection.
The lashing and hoisting points of steel beams are particularly important. Steel poles can be used when the steel beams are too long. There are many steel beams in this project with a maximum length of about 20m. A triangular hanging plate is used to enlarge the distance between the steel ropes to increase the angle of the steel ropes. Require. Schematic diagram of steel beam lashing.

 


Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
全自动糖衣机| 酵母抽提物喷雾干燥机| 高低温交变湿热试验箱| 定量包装秤| 教学演示| 压力传感器| SHELDON培养箱| 大鼠肝实质细胞| 电磁辐射检测| 科研实验外包| 四轮板式滑车| 氧气透过率测试仪| 有毒气体检测仪| 无纺布封口| 观光车蓄电池| 机械车位租赁[重庆甘肃贵州云南二手停车场设备出租]智能车库投资建设| 槽型光电开关| 微型| 光电式滚珠开关| 压簧式热电偶| 实验室大功率电动搅拌机| 船用工程黑体温度干体炉| 折光仪| 4200生物分析仪| 生物质水冷燃烧机| 钢结构厂家| 罗茨真空泵厂家| MT8852B| 镀锌钢筋| 粮食取样器| 川仪PDS| X荧光硫测定仪| 液氨泄漏报警器| 体系认证咨询| 外贸手表厂家| SV630B莱宝真空泵| rohs荧光分析仪| 托普云农植保仪器网| 药敏纸片| 半导体皮秒激光器| 荧光探针PCR试剂盒|