钢结构_钢结构厂房_钢结构平台_钢结构加工厂家--佛山市胜邦钢结构有限公司

Language:CHINESESENGLISH

Home > News > Analysis of key construction points of steel column and frame beam of high-rise steel structure
CONTACT US
  • Address:Pingtang Industrial District, Shipeng Village, Shishan Town, Nanhai District, Foshan City,
  • Phone:0757-81002668/0757-63323396
  • Fax:0757-81196682
  • Contact:Ben Zheng/13826981293 Kerry Lu/13751224830
  • E-mail:sbs@sbsprefabhouse.com
  • URL:http://www.sbshouses.cn

Analysis of key construction points of steel column and frame beam of high-rise steel structure

Time:[2021-8-25]  Hits:2108

Analysis of key construction points of steel column and frame beam of high-rise steel structure

1、 Analysis on key points of steel column construction of high-rise steel structure

Steel column is a vertical component that determines the floor height and the total height of the building, and its fabrication and processing needs to meet the corresponding specifications and standards. At the same time, the shrinkage deformation of the weld and the compression deformation caused by the vertical load need to be considered in the process of turning and blanking. Therefore, the turning and blanking length of the steel column is not equal to the design length, even if it is only a few millimeters, it can not be ignored. Moreover, when the sections of the upper and lower steel columns are completely equal, they are not allowed to be interchanged. It is required that each steel column shall be numbered differently and installed in place correctly. The welding of stiffener plate in rectangular or square steel column shall adopt nozzle electroslag welding according to the requirements of current specifications, and other forms such as opening on box plate and slot plug welding are not allowed.

2、 Analysis on key construction points of high-rise steel structure frame beam

In order to ensure that the joint area at the connection between the frame beam and the steel column has good ductility, connection reliability and floor height accuracy, during factory manufacturing, a cantilever beam (short corbel) is set at the position where the frame beam is located. The connection between the upper and lower flanges of the cantilever beam and the steel column adopts cut penetration weld, and the web adopts fillet weld. The frame beam is connected with the cantilever beam (short corbel) of the steel column, the upper and lower flanges are connected by the full penetration weld of the lining plate (also the arc striking plate), and the web is connected by high-strength bolts. Since the allowable deviation of reinforced concrete construction is far greater than the accuracy requirements of steel structure, when the frame beam is connected with reinforced concrete shear wall or reinforced concrete cylinder wall, the connecting plate of web can be opened with elliptical holes, which shall meet the requirements of hole edge distance. The blanking length of frame beam is also not equal to the design length, and the welding shrinkage deformation shall be considered. The welding shrinkage deformation can be calculated by empirical formula, and then checked according to the actual processing, so as to determine the exact length of the turning and blanking. High strength bolt connection or welding connection can be adopted for the connection of the upper and lower flanges of the frame beam. At present, most of them adopt full penetration welding connection with lining plate. During construction, the lower flange shall be welded first, and then the upper flange shall be welded. One end shall be spot welded for positioning, and then the other end shall be welded. The web is connected with high-strength bolts. It is necessary to fully understand whether friction type or pressure bearing type high-strength bolts are used in the design. The friction coefficient of friction type high-strength bolt should be selected reasonably. When using high-strength bolt group connection, the accuracy of hole position is very important. At present, template drilling and multi axis NC drilling are generally used for hole making. The former has low precision and the latter has high precision, so the latter should be given priority. When the formwork is used to make holes, the accuracy of the formwork shall be ensured to ensure the accuracy requirements of the assembly holes of high-strength bolts and site installation holes. In case of local deviation of hole position, reaming with reamer is only allowed. It is strictly prohibited to use gas cutting for hole expansion. If gas cutting is used for hole expansion, it shall be handled as a major quality accident.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
高频压力传感器| 滨州地坪施工| UV紫外线杀菌炉| 纳米砂磨机| 纯电动装载机| 高气压气体流量计| 低温水浴恒温振荡器| 冠州彩钢板| 电焊网片| 盐酸流量计| 米顿罗计量泵| 单向离合器| 危废暂存间| 液体比重仪| 汽车线束焊接机设备的制造商| 温度记录仪| 钢板防爆箱体| 米顿罗| 麻花式锚杆| 光纤压力传感器| 中国建材机械工业协会| 氢氟酸瓶口分液器| 恒温鼓风干燥箱| 试剂冻干小球| Accuro手泵| 铝型材挤压机| 安徽春辉压力变送器| 工业冷风机价格| 利茗减速机| PVC板厂家「价格低」| 宁波色差仪| 机械搅拌)| 双五点热封梯度仪| 无人值守地磅智能管理系统| 聚氨酯保温管厂家| PPH塑料袋式过滤器| 透明低温恒温槽| 电镀废水处理| 美国PE石墨管| 气动分度头| 铅屏风厂家|