Common problems of Foshan steel structure column base installation

Time:[2021-4-7]  Hits:2664

Installation of column base

 

(1) Embedded parts (anchor bolt) problems: overall or layout deviation; elevation error; screw thread without protective measures. The bolt holes on the bottom plate of the steel column are directly out of alignment, resulting in insufficient thread length.

 

Measures: the steel structure construction unit cooperates with the civil construction unit to complete the embedded parts work, before the concrete pouring and tamping. Relevant dimensions must be rechecked and fixed firmly.

 

(2) The phenomenon of anchor bolt not vertical: the horizontal degree of the base plate of frame column column foot is poor, the anchor bolt is not vertical, and the horizontal error of embedded anchor bolt is too large after foundation construction. The columns are not in a straight line after installation, which makes the appearance of the house difficult to see, brings errors to the steel column installation, and affects the structural stress, which does not meet the requirements of the construction acceptance specification.

 

Measures: the anchor bolt installation should adhere to the bottom plate leveling with the lower adjustment bolt, and then the secondary grouting of non shrinkage mortar, and the construction method abroad. Therefore, during the construction of anchor bolt, steel bar or angle steel can be used to fix anchor bolt. Welding into a cage, improving the support, or taking some other effective measures to avoid the anchor bolt moving one place when pouring the foundation concrete.

 

(3) Anchor bolt connection problems: the anchor bolt of column base is not tightened, the base plate is not welded with the bottom plate; some anchor bolts with 2-3 threads are not exposed.

 

Measures: Welding bolts and nuts shall be adopted; outside chemical anchor bolts, fire-proof coating and heat insulation treatment shall be added to prevent the anchorage performance from being affected by fire; observation data of foundation settlement shall be supplemented.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
电子粉质仪| 柯尼卡美能达授权代理商| 振动故障诊断监测系统| 压簧式热电偶| 在线式露点仪| 压片机冲头| HF酸分配器| 电加热元件| 全自动数控制丸机| ATOS上海办事处| TOA离子计| 生物制药旋转蒸发仪| 高温氧化铝| 数字示波器TDS3034C| 等离子电源| 圆形固相萃取装置| ChemChina| 二手集装箱| CINCON电源| 自净型试剂柜| 南京货架价格低| 全自动压力校验装置| ILS注射器| MTS办事处| 电子万能试验机| 万向球| 无极加强继电器| 电导率测试仪| 蜗轮丝杆升降机| 3351电容式差压变送器| 不锈钢电加热元件| 电机耐久测试系统| 汽车尾气氮氧化合物检测仪| 口服液洗烘灌联动线| 天津威乐水泵| 鞋底耐弯折试验机| 合肥代理记账| 原装ATOS电磁阀| 挥发物气体检测仪| 带接管道阻火单呼阀| 实验室磷酸根|