Analysis on Difficulties and Safety Precautions of Foshan Steel Structure Sandwich Construction

Time:[2017-1-4]  Hits:4802

Sandwich construction site in Foshan steel is often a small space, the main beam is difficult to enter, even after disconnection in the outside into the connection, the machine is not easy to use, hand-lift carry stitching after lifting.

1, take root
   Sandwich safety is one of the key "rooting", the so-called root is the new mezzanine roof load through the main beam radiation to the root, from the root spread to the original structure, like a tree without a strong root tree can not stand.

In the actual construction of the first to detect the media hardness. thickness. Reinforcement, etc., try not to interrupt the main hole when the hole, in strict accordance with the requirements of the depth of the process, diameter hole, according to the roof load configuration bolt. In the anchor must be cleared before the hole, otherwise it will seriously affect the anchorage strength, implant speed can not be too fast can cause drug mixing is not complete, too slow will cause running drugs, will reduce the pull force, after implantation According to the temperature before waiting for construction.

According to the total radiation of the main beam, the thickness and area of ​​the anchor plate are calculated. (The value of the anchor bar is higher than that of the high strength bolts, and the success rate of the reinforcing bar is low.) Of the reason) welding pallets or connecting plate to be split welding.

Installation of the anchor bolt to pull the experiment, the shear force can be carried out on the soil experiment, all anchor plate drilling hole to consider when the situation, can play less equipment, but not less than the design load. If the anchor plate and concrete beams or concrete columns can be gap between the filling or grouting material processing, all the anchor after solidification before loading the main beam.

2, the main beam

The main beam in the sandwich project is the safety key to the second, if a tree even the roots of the tree can no longer withstand external force is also in vain, the choice of the main beam and roof load, span is directly related to the span if you can choose small Cutting, primer and other treatment, to the site after the measurement of both ends of the anchor in the fine-cutting, sandwich works and other steel works is different from the majority of the beam purlin of the beam, or the H-beam steel beam to be polished, Because the box beam must be welded, high cost, weight, hoisting and transportation difficulties, the end of the attic mezzanine construction, the size of the structure of the beam, the length of the length of the indefinite length, so the measured after cutting, if the span of small to try to use steel,

3, connection

Foshan steel construction is the main steel beam connection, 1 welding, 2 high-strength bolted connection. In large projects generally use high-strength bolted or welded, because the venue and welding power to allow this is not to say, in the mezzanine site is often a small space, the main beam is difficult to enter, even after disconnection into the connection, mechanical easy to use Not on hand-lift carry stitching after lifting steel beam connection.

Foshan steel construction safety measures:

(1) construction operations should comply with safety operating procedures, must enter the scene with a helmet, smoking to the development of the smoking room, high-altitude operation of a good seat belt. To establish a prevention-oriented security awareness.

(2) check fire, fence and other safety facilities are perfect, imperfect to be trimmed or added.

(3) should be promptly cleaned up a variety of roads and roads of snow and ice, pay attention to anti-slip fall. Can not be promptly removed due to the laying of straw, wood and other non-slip measures.

(4) sand electric heating pipe should be taken to protect the grounding measures to prevent leakage.

(5) open fire should be away from combustible materials, or to take isolation measures. Strict implementation of the use of fire card system. And carry fire bucket, set up to see the fire.

(6) to protect the safety of workers, dormitory is prohibited within the electric furnace or other dangerous electrical heating equipment.

(7) to prevent frostbite in winter facilities, or gas poisoning incidents.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
自相关仪超短脉冲测量仪| 重庆市沃利克环保设备| 排屑机| 不锈钢防爆控制箱| 智能化开关特性测试仪| 生物质木块颗粒熔铝炉| 调节池框式搅拌机| 铜线腐蚀测定仪| CASELLA科赛乐| 华铝建筑门窗铝型材| 高频焊翅片管| 钓鱼艇| 油泵齿轮泵组合泵| 一体化振动探头| 苏州机床排屑机| 磷酸铁锂浸出料液除钙镁| 厂房车间通风降温设备| 变频介质损耗测试仪| 价格(研发制造)| 上海拉力试验机| 富士侧流风机| 德州铝合金电梯门套| 佛山房屋倾斜纠偏扶正| 冷光源人工气候培养箱| 电镀金银镍铜锡| VOCs深冷冷凝回收| 次氯酸钠发生器| 单向液压锁| 亨士乐计数器| 工业省电空调厂家| MiltonRoy米顿罗电磁泵| 安捷伦信号发生器维修| 2205材质截止阀| 人胰岛素elisa试剂盒| 眼科剪刀| 恒温恒湿机.恒温恒湿柜.防潮柜.氮气柜| 油侵式试验变压器| HYDAC继电器| 丝攻研磨机| 邯郸通风管道厂家| 深低温保存箱|