Steel Works how measures were rain

Time:[2016-8-6]  Hits:4153


Foshan Steel Company - Steel Katsukuni in the implementation of a steel works, when more or less met with some rain and even the rain when the rain this time how to conduct it? Steel Katsukuni now hears some experience of it!


First, in the implementation of structural steelwork will arrange for someone to keep abreast of the weather, rainy weather early grasp. Then arrange for someone in the field of special on-site inspection, so that you can not meet in time for some non-standard place rain or rectification. To note here is that, for those who want to be lightning-round check.


1, the module is most likely to be on a rainy day rain soaked destroyed before rain is necessary to use plastic sheeting to cover the template tight, when rain formwork construction, we must stay clean mouth or at the outlet in the template.


2, rain will cause corrosion of steel. General Steel Company Foshan Steel wins in the rain on the state will not be welded steel.


3, encountered heavy rain, stop concrete production. Good drainage work in the field, already pouring concrete covered with plastic sheeting, so it will not affect the quality of the project. Pouring concrete in the water within the template can be implemented to clean up. Rainy season, the water will adjust concrete and concrete mixing station.


4, rain can not be bolted in the rainy season, rain guarantee construction workers, construction electrical safety. Special circumstances, should stop high-altitude operations, and construction workers evacuated to safe areas, closed gates.


5, do not take the steel erection established grille. For lifting the member, member must maintain dry. Encountered strong winds, high altitude lifting and stop supporting the installation process.


6, rain is best not to open-air steel welding, the weld seam finish, insulation work to strengthen, not to cause embrittlement of the weld.


7, in five or more wind, rain, fog stopped the installation of high-strength bolts.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
汽车线束焊接机设备的制造商| 多功能吸入暴露染毒柜系统| 电子包装秤| HORIBA四线制分析仪| 拉力试验机| 威固德防爆型电动执行器| 考马斯亮蓝G250| 切屑粉碎机| 漏水检测仪| 盐酸流量计| 医用品包装机| 微波固体流量开关| 登高平台消防车专修| 温度巡检仪| 标线厚度测定仪| 晶圆加热盘| 钢管水压试验机| 装修除味除甲醛| 中山广州流水线| 梁山融悦二手设备经营部| 安全网拉力试验机| 美国力可LECO红外光源| 型钢| 成都生活污水处理设备| 多探头数字式照度计| 矿用隔爆型涡轮流量传感器| 真空泵保养| elektrophysik测厚仪| 安捷伦信号发生器维修| 景区污水处理设备| 创力掘进机配件| 推进桨式搅拌器| 电子简支梁冲击试验机| 船用电动执行器| 高强螺栓抗滑移系数检测仪| 多功能气候环境试验室| 柴油十六烷值测定仪| 科尔帕默蠕动泵| 氢氟酸瓶口分液器| 气体泄漏成像仪| 金属硬密封固定球阀|