Foshan main steel members (a)

Time:[2016-5-14]  Hits:4331

1 Preparations
(1), the former Foshan steel processing, construction workers prepared by the process of order by the chief engineer for approval. Carefully check process preparation of each process, and to do the work of peer review process and made drawings.
(2) for processing a variety of materials and equipment needed to carry out checks, process equipment shall comply with the technical rules.
(3), construction workers well in advance of the work of the technical disclosure of the procedures.
(4), the operator of the induction training and assessment well in advance of the special types of qualification confirmation must be certified.
(5), should be checked before lofting master processing map and process requirements, identify problems in time to the departments concerned.


2 steel members Stake
(1), the steel member in stakeout procedures to verify the number of Foshan and steel fittings, material specifications, model, size, etc., and then the ingredients, crossed loft, stacked separately.
(2), an important node in the size of the figure processing structure or component can be placed or actual sample calculation check.
You must check the steel specifications, materials, lot before (3), item number, and remove the steel surface oil, dirt and other dirt.

3 cleavage
(1), beam flange plate, web and end plate after lofting use CG1-100 semi-automatic cutting machine, to avoid the steel plate member is not straight edge, lack of edge broken corner phenomenon; ribs and webs with rigid support Shears shearing machine; profile cutting by hand or machine cutting wheel.
(2), should be before cutting steel surface rust, oil, etc. clean.
(4), sheet metal gas cutting should be carried out on a dedicated platform.


4 hole system
(1), joints and connections of steel members are connected by high strength bolts. Aperture position, size, requires a high degree of precision. Using drilling drilling.
(2), using the drilling jig and pack sets of drilling, hole making application fixtured to prevent the jig or laminates bit string.
(3) After completion of the application system hole hole burr grinder completely clear, and must not damage the base material.


5 assembly
(1), prior to assembly of the lower parts should be corrected, or the press can be used for thick steel plate flame heating correction.
(2), members using flange straightening machine for the production of beams correction.
(3), the assembly members should determine a reasonable order of assembly according to its structure, welding method and welding sequence and the like. To reduce welding deformation.
(4), this project steel columns, steel beams are on the internet a 1: 1 ratio put real kind, according to the processing of all the parts on the assembly diagram.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
住人大波纹箱| 旋转环盘电极RRDE| 恶臭在线监测仪| 中央空调维修厂家| 地埋式积水监测预警系统| 固化剂造粒机| 济南型钢| 装岩机| 塑料背心袋| 深圳全网推广| 伞钻| 空气芯滤| 广东| 玻璃厌氧发酵罐| 便携式X射线应力分析仪| 纸张抗张强度试验仪| 液氮冷冻设备厂家| 德州铝合金电梯门套| 二手浓缩提取机组| 运动地板厂家| 实验室智能硬件平台| 看门狗真空断路器价格| 看门狗真空断路器价格| 家用自吸泵| KOHKI油压快换接头| 景区大气负氧离子监测系统| technical| 植生毯| 节能防火窗| 交通信号灯厂家| 玻纤吊顶板| 智能型蓄电池参数测试仪| 提水式曝气机| wms智能称重| 盘装氧量分析仪| 高气压气体流量计| 倒置式屋面施工| Honsberg流量计| 二手车铣复合机床| 横河高精度功率分析仪| 红外线电热灭菌器|