Guangzhou Steel teach you: Steel supervision next station control points

(1) Before the construction supervisors to deal with the approach of materials (steel, high-strength bolts) check, approach the material must have factory quality certificate and sampling site is intended for use after passing inspection, welding rod, wire, flux should meet the requirements .
(2) Check the installation of the production staff of technical welder qualification certificate, so certificates.
Welding income margin, cutting and other allowance and column in compression load deformation value (3) the material according to process requirements, making installation reserved.
(4) member when assembled, to prevent distortions member bagging inaccurate.
(5) welding to adhere to a thickness greater than 50mm carbon structural steel and low-alloy structural steel before welding larger than 36mm preheat hot after welding performed.
(6) the quality of the weld seam inspection in addition to dimensions, surface quality inspection, but also check the internal weld defects, according to the requirements of the drawing to determine the grade of weld quality grade and defects NDT.
(7) Before installing the column, a detailed examination of the relative position of the axis of the anchor bolts and offset.
(8) a single vertical column of steel columns, with one column capitals elevation sections deviations on the wrong port value under the column connection.
(9) Guangzhou Steel steel member during product delivery, product quality must have approval and certification, in order to be sent to the installation site, after installation departments for product acceptance Engineer focused on installation and connection components in place to check on the situation and members steel members connected with the concrete peg holes reservation wear bars.

Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号
一氧化氮泄露报警器| 国产分光光度计| 工业用绝缘监测装置| 高压电缆故障测试仪| 多功能气浴恒温摇床| 氨水在线浓度分析仪| 细胞膜| 万向轴承| 鼎阳1G示波器| HMW82| 水质toc分析仪| 水质在线溶解固体TDS分析仪| 合肥代理记账| 心肺复苏医疗教学模拟人| 滁州电梯| 小型催化剂挤条机| 气体泄漏报警控制器| 多合一气体检测仪| 卡尔费休水分仪| 绝缘杆耐压| Emfab过滤膜7221| 办事处| 杭州二手搪瓷反应釜| 拉力试验机| 进口粘度计| 气环式高压鼓风机| 复合材料| KURABO仓纺浓度计| 温室大棚育苗洒水车| 精密仪器室装修定制| 电子磅解码器| 纯电动装载机| 河北睿建试验仪器设备厂| 建筑气密性测试系统| 陶瓷断裂模数测定仪| 防霜式玻璃板液位计| 三洋二氧化碳培养箱| 包装堆码试验机| 光散射检测器| 真空校验设备| 电动执行器阀门|